SAP PP What is MRP Area And How Is It defined

What
is MRP Area And How Is It defined

http://www.erpgreat.com/production/what-is-mrp-area-and-how-is-it-defined.htm

 

What
is MRP Area And How Is It defined

 

What is MRP Area. How it is defined? What are the
points to be considered while defining a MRP Area?

The MRP area is an organizational unit for which
material requirements planning can be carried out independently outside of
total plant level MRP run which is done using MD01 for entire plant. by
creating a specific scope of planning and is maintained in the MRP view of
the material master

But first you need to create it in SPRO and if needed
assign the storage locations or materials masters to the mrp area and MRP
with MRP areas for the material is not activated until the material has been
assigned to an MRP area. If you have not assigned a material to an MRP area,
that is, you have not created an MRP area segment in the material master, the
material will continue to be planned in the plant MRP area only.

Basically, there are three types of MRP area:

1. Plant MRP Area

The plant MRP area initially contains the plant
together with all its storage locations and stock with subcontractors. 
When you have defined the other 2 types of MRP areas for storage locations
and for subcontractors and you have assigned the materials, the plant MRP
area is reduced by exactly this number of subcontractors and storage
locations. This is because they are now to be planned separately.

2. MRP Areas for Storage Locations

You can define an MRP area that consists of a
particular storage location, by creating an MRP area and assigning the
storage location to it. Material requirements for this storage location are
then planned separately from the rest of the plant.

You can also group several storage locations into one
MRP area, by creating an MRP area and assigning the storage locations to it.
These storage locations are then planned together.

3. MRP Areas for Subcontractors

You can also define an MRP area for each subcontractor.

A subcontractor may be assigned to only one MRP
area. 

Advantages of using MRP area and highlights.

1. You can carry out MRP specifically for the
determined MRP areas. This enables you to carry out differentiated material
requirements planning.

2. Finished products and important assemblies intended
for make-to-order or engineer-to-order production are always planned in the
plant MRP area

3. The planning run takes into account the planning
with MRP areas as follows:

4. If you do not enter a separate scope of planning,
the system plans the whole plant, that is, all MRP areas in the plant, during
the total planning run. If you want to carry out a total planning run for a
particular MRP area only, you must specify the required MRP area in the scope
of planning.

5. During single-item, multi-level planning, the system
plans the selected material in the MRP area entered. In addition, the system
takes into account planning file entries from other MRP areas, for example,
if the material is to be procured using stock transfer.

6. During single-item, single-level planning, the
system plans the selected material in the MRP area entered only.

Now, for running the cycle for MRP areas, we need to
define in SPRO.

IMG -> Production Planning -> MRP -> Master
data -> Define MRP Areas

Specify Area types 

01 - Plant MRP Area,

02 - Storage Location MRP Area

03 - Sub contractor MRP Area.

After defining MRP area, assign the material to the
specific MRP area in the MRP1 view of the Material master and define the MRP1
& 2 views specific for those areas.

Enter the requirements for the specific MRP areas, if
you do not enter the MRP area, MRP area by default will be picked as Plant
MRP area.

Also, need to run MRP, by entering appropriate MRP
area.

Stock/Rqmts list to be selected by entering the MRP
area in the selection screen.

 

时间: 2024-08-15 00:34:44

SAP PP What is MRP Area And How Is It defined的相关文章

SAP PP MRP Area 基础知识

SAP PP Basics of MRP Area   https://blogs.sap.com/2015/07/01/basics-of-mrp-area/   The purpose of this document is to explain the basics of MRP area, steps involved in activating MRP area and to use it in different possible ways. As we know MRP runs

SAP PP 启用Storage Location Level 的MRP Area之后对于SD的影响初探

SAP PP 启用Storage Location Level 的MRP Area之后对于SD的影响初探   Storage location level MRP Area CN07_WS setting:     Finished product material: F000201336. The initial stock for this material:   In 1001(existing site), we have 4400 EA, in 1003 (new site), we

SAP PP 新建工厂后的MRP运行

SAP PP 新建工厂后的MRP运行   [Issue] 我参考标准工厂0001,配置新的工厂Z001后,当我对一个物料用MD02运行MRP时,是可以跑出plan order的.而如果我用MD40或者MD01(或后台MDBS)去批量运行MPS(MRP)时,却无法跑出一个plan order,而且从MRP的运行日志来看,运行时间为0秒.Why?   [Solution] 在后台OMDU(路径:SPRO-生产-物料需求计划-计划文件条目-激活MRP)或者前台事务MDAB中创建该工厂的计划条目,然后用

SAP PP 计划外发料与计划内发料在WM层面的差异初探

SAP PP 计划外发料与计划内发料在WM层面的差异初探   Process order header material: HR0072 BOM item materials: RR0078 R0078A R0880A   Control cycle master data: they are all pick parts.   create &release process order, M36040         Release process order, TR was created:

SAP PP 流程订单后续的备料TO确认后想改某个原料的批次号然后重新备料,如何做?

SAP PP 流程订单后续的备料TO确认后想改某个原料的批次号然后重新备料,如何做?   Process order: M35040   The TR document 271120 for this process order,   LT04 to convert TR to TO,     Save it. Batch determination was conducted. Once TO was confirmed,   the batch of components was updat

SAP PP Availability Check for Batches

SAP PP Availability Check for Batches         这里定义生产计划做ATP检查时候是否考虑Restricted Stock,      

SAP QM 不上SAP PP模块可以做成品的入库检验查吗?

SAP QM 不上SAP PP模块可以做成品的入库检验查吗?   可以实现的.前提是你激活了QM模块相关的配置/主数据. 1.QM 准备:物料主数据/检验计划.检验特定等 2. MB1C/MB11: Movement type 521

SAP PP 为工单确认时自动做收货的设置

SAP PP 为工单确认时自动做收货的设置   TCode: OP67         Micro Message: JINYULIN_SH_

SAP PP 工序委外业务里的PR Type由OPJP里配置 !

SAP PP 工序委外业务里的PR Type由OPJP里配置 !   TCode: OPJP Next,     微信号:JINYULIN_SH_ QQ:2806032155